ABATEMENT SCHEDULED – SEPT 29 2022

We posted a notice on September 23, advising residents that the Board of Managers approved the abatement of the popcorn ceilings in several locations and the reasons for doing the work.

We compiled a complete schedule and wanted residents to know when they can expect the work to take place in their area. Specific details will be sent directly to those impacted by the work but in the meantime, here is the scheduled through October 19, 2022, when we expect the work to be completed.

Friday, September 30 — 12th floor Princeton from the elevator lobby area down to units 1205/1212.

Monday, October 3 — 7th floor Harvard from the trash room area down to units 721/724

Tuesday, October 4 — 8th floor Harvard from the trash room area down to units 821/824

Wednesday, October 5 — 11th floor Princeton from the elevator lobby area down to units 1105/1112

Thursday, October 6 — 10th floor Princeton from the elevator lobby area down to units 1005/1012

Friday, October 7 — 9th floor Princeton from the elevator lobby area down to units 905/912

Monday, October 10 — 8th floor Princeton from the elevator lobby area down to units 805/812

Tuesday, October 11 — 7th floor Princeton from the elevator lobby area down to units 705/712

Wednesday, October 12 — 6th floor Princeton from the elevator lobby area down to units 605/612

Thursday, October 13 — 5th floor Princeton from the elevator lobby area down to units 505/512

Friday, October 14 — 4th floor Princeton from the elevator lobby area down to units 405/412

Monday, October 17 — 3rd floor Princeton from the elevator lobby area down to units 305/312

Tuesday, October 18 — 2nd floor Princeton from the elevator lobby area down to unit 205 and the storage lockers

Wednesday, October 19 — 1st floor Princeton from the elevator lobby area down to units 105 and the storage lockers

Residents will not be able to access the areas while the work is taking place. If you live in an area where the work is taking place, we strongly suggest you leave your unit for the day. If not, you will need to use the stairs in Fire Tower D for the Princeton building and Fire Tower A in the Harvard building when the work is being conducted on that floor. As you will not be able to access the elevator area on the floor where the work is taking place.

The work is expected to start at 8 am and continue until approximately 6 pm. The work area will be COMPLETELY SEALED OFF until the work is completed that day.